Roebuck Retail Park, Stevenage

POSTED ON: 10/07/2021

Risk Management Limited were employed on behalf of Craddys to undertake a Phase I, Phase II Site Investigation at an existing retail park to inform the design and construction of additional units.

Intrusive fieldwork consisted of 4 No light-percussion boreholes up to 7m depth, 3 No. hand and mechanically excavated Trial Pits, 4 No. MEXE probe test, 2 No. falling head permeability tests and land-borne gas monitoring.

Laboratory testing was undertaken in line with the Consulting Engineers, specification and included Particle Size Distribution tests, Asbestos identification, pH and Sulphate tests and Soil and Groundwater Contamination tests.

Groundwater and gas monitoring was undertaken.

BACK TO POSTS