Belgravia, London

POSTED ON: 23/05/2022

RML were commissioned to carry out both a Phase I Desk study and Phase II Site investigation in Belgravia, London for the complete renovation of a building, while retaining the external facade.

Walkover Survey by RML Engineer

A walkover survey was carried out by an RML Engineer to establish if contamination is present from any undocumented practice or industrial use of the land and surrounding land and if necessary to confirm the accuracy of the information obtained from elsewhere as part of the Preliminary Risk Assessment (PRA) data gathering process . A visual assessment of the land to check for signs of industrial activity, landfilling, fly tipping , fuel storage, fuel tanks, asbestos related materials or any land contamination was undertaken and a photographic record made to provide evidence to show the condition of the land at the time of the Walkover Survey.

Phase I Environmental Risk Assessment

Environmental data, comprising geo-environmental hazards, hydrology and hydrogeology, was obtained for the current site covering an area of up to 1000m from the site boundary.

Historical Maps

Historical Ordnance Survey maps were also obtained for the site, as part of the PRA data gathering process. These maps were used to inform of potential historical contaminative processes.

Fieldwork

Fieldwork was undertaken in line with British Standards BS 5930:2015+A1:2020. 1 No. Light Percussion Borehole, 1 No. ‘cut-down’ Cable Percussion Borehole, 1 No. Drive-In-Sampler Borehole, Falling Head Permeability Tests and Land-Borne Gas Monitoring were undertaken as part of investigation.

Laboratory Testing

Natural Moisture Content, Quick Undrained Triaxial Compression Test, Particle Size Distribution, pH & Sulphate tests, Chemical analysis, Asbestos Identification and Waste Acceptance Criteria (WAC) tests were the Laboratory tests undertaken for this project.

BACK TO POSTS